lag time

A delay between tasks that have a task relationship. For example, lag time causes the successor task in a finish-to-start relationship to begin some time after its predecessor task concludes.

lead time

An overlap between tasks that have a task relationship. For example, lead time causes the successor task in a finish-to-start relationship to begin before its predecessor task concludes. In the Project interface, you enter lead time as negative lag time.

line manager

A manager of a group of resources; also called a functional manager. A line manager might also have project management skills and responsibilities, depending on the organization’s structure.

linkA logical relationship between tasks that controls sequence and dependency. In the Gantt Chart and Network Diagram views, links appear as lines between tasks.




Microsoft Office Project 2003 Step by Step
MicrosoftВ® Office Project 2003 Step by Step (Step by Step (Microsoft))
ISBN: 0735619557
EAN: 2147483647
Year: 2003
Pages: 199

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net