To set the project status date, page 392
1 On the Project menu, click Project Information.
2 In the Project Information dialog box, in the Status Date box, type or click the status date you want, and click OK.
To view earned value schedule indicators, page 392
1 On the View menu, click More Views.
2 In the More Views dialog box, click Task Sheet, and then click Apply.
3 On the View menu, point to Table: Entry, and click More Tables.
4 In the More Tables dialog box, click Earned Value Schedule Indicators, and click Apply.
To view earned value cost indicators, page 394
1 On the View menu, click More Views.
2 In the More Views dialog box, click Task Sheet, and then click Apply.
3 On the View menu, point to Table: Entry, and click More Tables.
4 In the More Tables dialog box, click Earned Value Cost Indicators, and click Apply.
To create an Earned Value visual report, page 398
1 On the Report menu, click Visual Reports.
2 Click the Assignment Usage tab.
3 Click Earned Value Over Time.
4 In the Select level of usage data to include in the report box, select the time interval you want for reporting.
5 Click View.
6 In Excel, adjust the PivotTable and chart as needed.