Questions from Chapter Ten


1.

The ________ is the document that starts the entire Project Time Management process.

A.

Charter

B.

SOW

C.

RFP

D.

Scope Statement


2.

Decomposition of the Scope Statement results in the ________.

A.

Project plan

B.

WBS

C.

SOW

D.

Schedule


3.

You break down the WBS into smaller ________ to get detail so that you can construct a schedule.

A.

Work packages

B.

Time components

C.

Sections

D.

Issues


4.

When using decomposition in activity definition, the final output is:

A.

Deliverables

B.

Work packages

C.

Activities or action steps

D.

Schedule


5.

Updates to the WBS during activity definition are often called:

A.

Supporting detail

B.

Refinements

C.

Updates

D.

Activities


6.

A form of progressive planning is called:

A.

Scheduling

B.

Charting

C.

Expanded trial

D.

Rolling wave


7.

The major output from activity definition is:

A.

The schedule

B.

The activity list

C.

WBS

D.

SOW


8.

Other outputs from activity definition are:

A.

Activity attributes, Milestone lists

B.

WBS, SOW

C.

Technical requirements, and the WBS

D.

Activity costs, schedule costs


9.

Milestones are:

A.

Activities with durations

B.

Significant events in the project life cycle

C.

Cost measurements

D.

Denote start and finish of all activities


10.

Three types of dependencies are mandatory, discretionary, and ________.

A.

Easy

B.

Planned

C.

Internal

D.

External


11.

How long is the duration for a milestone?

A.

0 days

B.

3 days

C.

It depends

D.

5 days


12.

The type of dependency that is used by Microsoft Project is a ________ dependency.

A.

Start-to-finish

B.

End-to-end

C.

Finish-to-start

D.

Start-to-end


13.

Starting a new computer system before turning the old one off is an example of a(n) ________ dependency.

A.

Start-to-finish

B.

End-to-end

C.

Finish-to-start

D.

Natural


14.

Which Network Diagramming Method uses dummy activities?

A.

PDM

B.

GERT

C.

PERT

D.

ADM


15.

PDM is also known as what?

A.

Activities on nodes

B.

Activities dependencies

C.

Activities on arrows

D.

Activities sequencing


16.

PDM stands for:

A.

Positive Daily Mechanisms

B.

Process Diagramming Method

C.

Precedence Daily Management

D.

Precedence Diagramming Method


17.

Conditional branches can be found in:

A.

GERT

B.

PERT

C.

PDM

D.

AON


18.

A schematic display of the project's activities and the logical relationships among them is a(n) ________.

A.

Technically difficult process

B.

Working Schedule

C.

Project network diagram

D.

Schedule diagram


19.

________ are a high-level compilation of the tasks below them.

A.

WBS

B.

Summary tasks

C.

Schedules

D.

PDM


20.

The project plan is developed by:

A.

The manager of project managers

B.

Executive management

C.

The project team and manager

D.

Sponsors


21.

The project schedule is developed in the ________ phase.

A.

Execution

B.

Initiation

C.

Planning

D.

Conceptual


22.

Estimating databases and other historical data are examples of ________ that might be helpful in estimating durations.

A.

Records

B.

Organizational assets

C.

Written data

D.

Electronic information


23.

Top-down estimating is also known as ________ estimating.

A.

Organizational

B.

Simple

C.

Analogous

D.

Primary


24.

Which technique below is the most common simulation technique?

A.

GERT

B.

Monte Carlo

C.

Linear Analysis

D.

Decompression


25.

Rules of thumb are known as ________.

A.

Leveling Heuristics

B.

Common sense

C.

Problem solvers

D.

Monte Carlo analysis


26.

Monte Carlo simulation is done using ________ scenarios.

A.

Simple

B.

Technical

C.

Common

D.

Multiple


27.

What tasks would you Fast Track to shorten the project duration in the Critical Path in Figure 10-9?

A.

E & G

B.

B, D, & E

C.

C & F

D.

C & G


28.

Doing more activities in parallel is called ________.

A.

Fast Tracking

B.

Schedule clearing

C.

Compressed work

D.

Planning compression


29.

Bar charts do not show ________.

A.

Time constraints

B.

Dependencies

C.

Partial tasks

D.

All of the above


30.

The approved project schedule is called the:

A.

Sponsored schedule

B.

Performance schedule

C.

Baseline schedule

D.

Approved schedule


31.

Anything done to bring expected future schedule performance in line with the project plan is known as ________.

A.

Replanning

B.

Schedule arrangement

C.

Corrective actions

D.

Rebaselining


32.

If you update the schedule, the updates must be approved by the ________.

A.

Project manager

B.

Project Team

C.

Line management

D.

Sponsor


33.

Revisions are a special type of schedule updates that make changes to:

A.

Costs

B.

Resources

C.

Same as Fast Tracking

D.

Start/Finish Dates


34.

Rebaselining should occur only if the current baselines ________.

A.

Are off by 10%

B.

Are off by 20%

C.

Make no sense

D.

Are bad




Passing the PMP Exam. How to Take It and Pass It
Passing the PMP Exam: How to Take It and Pass It: How to Take It and Pass It
ISBN: 0131860070
EAN: 2147483647
Year: 2003
Pages: 167
Authors: Rudd McGary

flylib.com © 2008-2017.
If you may any questions please contact us: flylib@qtcs.net