1. | The ________ is the document that starts the entire Project Time Management process. | A. | Charter | | B. | SOW | | C. | RFP | | D. | Scope Statement |
|
2. | Decomposition of the Scope Statement results in the ________. | A. | Project plan | | B. | WBS | | C. | SOW | | D. | Schedule |
|
3. | You break down the WBS into smaller ________ to get detail so that you can construct a schedule. | A. | Work packages | | B. | Time components | | C. | Sections | | D. | Issues |
|
4. | When using decomposition in activity definition, the final output is: | A. | Deliverables | | B. | Work packages | | C. | Activities or action steps | | D. | Schedule |
|
5. | Updates to the WBS during activity definition are often called: | A. | Supporting detail | | B. | Refinements | | C. | Updates | | D. | Activities |
|
6. | A form of progressive planning is called: | A. | Scheduling | | B. | Charting | | C. | Expanded trial | | D. | Rolling wave |
|
7. | The major output from activity definition is: | A. | The schedule | | B. | The activity list | | C. | WBS | | D. | SOW |
|
8. | Other outputs from activity definition are: | A. | Activity attributes, Milestone lists | | B. | WBS, SOW | | C. | Technical requirements, and the WBS | | D. | Activity costs, schedule costs |
|
9. | Milestones are: | A. | Activities with durations | | B. | Significant events in the project life cycle | | C. | Cost measurements | | D. | Denote start and finish of all activities |
|
10. | Three types of dependencies are mandatory, discretionary, and ________. | A. | Easy | | B. | Planned | | C. | Internal | | D. | External |
|
11. | How long is the duration for a milestone? | A. | 0 days | | B. | 3 days | | C. | It depends | | D. | 5 days |
|
12. | The type of dependency that is used by Microsoft Project is a ________ dependency. | A. | Start-to-finish | | B. | End-to-end | | C. | Finish-to-start | | D. | Start-to-end |
|
13. | Starting a new computer system before turning the old one off is an example of a(n) ________ dependency. | A. | Start-to-finish | | B. | End-to-end | | C. | Finish-to-start | | D. | Natural |
|
14. | Which Network Diagramming Method uses dummy activities?
|
15. | PDM is also known as what? | A. | Activities on nodes | | B. | Activities dependencies | | C. | Activities on arrows | | D. | Activities sequencing |
|
16. | PDM stands for: | A. | Positive Daily Mechanisms | | B. | Process Diagramming Method | | C. | Precedence Daily Management | | D. | Precedence Diagramming Method |
|
17. | Conditional branches can be found in:
|
18. | A schematic display of the project's activities and the logical relationships among them is a(n) ________. | A. | Technically difficult process | | B. | Working Schedule | | C. | Project network diagram | | D. | Schedule diagram |
|
19. | ________ are a high-level compilation of the tasks below them. | A. | WBS | | B. | Summary tasks | | C. | Schedules | | D. | PDM |
|
20. | The project plan is developed by: | A. | The manager of project managers | | B. | Executive management | | C. | The project team and manager | | D. | Sponsors |
|
21. | The project schedule is developed in the ________ phase. | A. | Execution | | B. | Initiation | | C. | Planning | | D. | Conceptual |
|
22. | Estimating databases and other historical data are examples of ________ that might be helpful in estimating durations. | A. | Records | | B. | Organizational assets | | C. | Written data | | D. | Electronic information |
|
23. | Top-down estimating is also known as ________ estimating. | A. | Organizational | | B. | Simple | | C. | Analogous | | D. | Primary |
|
24. | Which technique below is the most common simulation technique? | A. | GERT | | B. | Monte Carlo | | C. | Linear Analysis | | D. | Decompression |
|
25. | Rules of thumb are known as ________. | A. | Leveling Heuristics | | B. | Common sense | | C. | Problem solvers | | D. | Monte Carlo analysis |
|
26. | Monte Carlo simulation is done using ________ scenarios. | A. | Simple | | B. | Technical | | C. | Common | | D. | Multiple |
|
27. | What tasks would you Fast Track to shorten the project duration in the Critical Path in Figure 10-9? | A. | E & G | | B. | B, D, & E | | C. | C & F | | D. | C & G |
|
28. | Doing more activities in parallel is called ________. | A. | Fast Tracking | | B. | Schedule clearing | | C. | Compressed work | | D. | Planning compression |
|
29. | Bar charts do not show ________. | A. | Time constraints | | B. | Dependencies | | C. | Partial tasks | | D. | All of the above |
|
30. | The approved project schedule is called the: | A. | Sponsored schedule | | B. | Performance schedule | | C. | Baseline schedule | | D. | Approved schedule |
|
31. | Anything done to bring expected future schedule performance in line with the project plan is known as ________. | A. | Replanning | | B. | Schedule arrangement | | C. | Corrective actions | | D. | Rebaselining |
|
32. | If you update the schedule, the updates must be approved by the ________. | A. | Project manager | | B. | Project Team | | C. | Line management | | D. | Sponsor |
|
33. | Revisions are a special type of schedule updates that make changes to: | A. | Costs | | B. | Resources | | C. | Same as Fast Tracking | | D. | Start/Finish Dates |
|
34. | Rebaselining should occur only if the current baselines ________. | A. | Are off by 10% | | B. | Are off by 20% | | C. | Make no sense | | D. | Are bad |
|