|
|
||||||
Because of the unique nature of constructed facilities, it is almost imperative to have a separate price for each facility. The construction contract price includes the direct project cost including field supervision expenses plus the markup imposed by contractors for general overhead expenses and profit. The factors influencing a facility price will vary by type of facility and location as well. Within each of the major categories of construction such as residential housing, commercial
The basic structure of the bidding process consists of the formulation of detailed plans and specifications of a facility based on the objectives and requirements of the owner, and the
Detailed plans and specifications are usually prepared by an architectural/engineering firm which oversees the bidding process on
Instead of
The fixed percentage or fixed fee is determined at the outset of the project, while variable fee and target estimates are used as an incentive to reduce costs by sharing any cost savings. A guaranteed maximum cost arrangement imposes a penalty on a contractor for cost overruns and failure to complete the project on time. With a guaranteed maximum price contract, amounts below the maximum are typically shared between the owner and the contractor, while the contractor is responsible for costs above the maximum.
In residential construction, developers often build
Some owners use in-house labor forces to perform a substantial amount of construction, particularly for addition, renovation and repair work. Then, the total of the force-account charges including in-house overhead expenses will be the pricing arrangement for the construction.
Back to top
Provisions for the allocation of risk among parties to a contract can appear in
The language used for specifying the risk assignments in these areas must conform to legal requirements and past interpretations which may vary in different jurisdictions or over time. Without using standard legal language, contract provisions may be unenforceable. Unfortunately, standard legal language for this purpose may be difficult to understand. As a result, project managers often have difficulty in interpreting their particular responsibilities. Competent legal counsel is required to
Standard forms for contracts can be obtained from numerous sources, such as the American Institute of Architects (AIA) or the Associated General Contractors (AGC). These standard forms may include risk and responsibility
The three examples appearing below illustrate contract language resulting in different risk assignments between a contractor (CONTRACTOR) and an owner (COMPANY). Each contract provision
Example 8-1: A Contract Provision Example with High Contractor Risk
"Except where the sole negligence of COMPANY is involved or alleged, CONTRACTOR shall indemnify and hold harmless COMPANY, its officers,agents and employees, from and against any and all loss, damage, and liability and from any and all claims for damages on account of or by reason of bodilyinjury , including death, not limited to theemployees of CONTRACTOR, COMPANY, and of any subcontractor or CONTRACTOR, and from and against any and all damages to property, including property of COMPANY and third parties, direct and/or consequential, caused by or arising out of, in while or in part, or claimed to have been caused by or to have arisen out of, in whole or in part, an act of omission of CONTRACTOR or its agents, employees,vendors , orsubcontractors , of their employees or agents in connection with the performance of the Contract Documents, whether or not insured against ; and CONTRACTOR shall, at its own cost and expense, defend any claim, suit, action or proceeding, whether groundless or not, which may be commenced against COMPANY by reason thereof or in connection therewith, and CONTRACTOR shall pay any and alljudgments which may be recovered in such action, claim, proceeding or suit, and defray any and all expenses, including costs and attorney's fees which may be incurred by reason of such actions, claims,proceedings , orsuits ."
Comment: This is a very burdensome provision for the contractor. It makes the contractor responsible for practically every conceivable occurrence and type of damage, except when a claim for loss or damages is due to the sole negligence of the owner. As a practical matter, sole negligence on a construction project is very difficult to ascertain because the work is so inter-twined. Since there is no dollar limitation to the contractor's exposure, sufficient liability coverage to cover worst scenario risks will be difficult to obtain. The best the contractor can do is to obtain as complete and broad excess liability insurance coverage as can be purchased. This insurance is costly, so the contractor should insure the contract price is sufficiently high to cover the expense.
Example 8-2: An Example Contract Provision with Medium Risk Allocation to Contractor
"CONTRACTOR shall protect, defend, hold harmless, and indemnify COMPANY from and against any loss, damage, claim, action, liability, or demand whatsoever (including, with limitation, costs, expenses, and attorney's fees, whether for appeals orotherwise , in connection therewith), arising out of any personal injury (including, without limitation, injury to any employee of COMPANY, CONTRACTOR or any subcontractor), arising out of any personal injury (including, without limitation, injury to any employee of COMPANY, CONTRACTOR, or any subcontractor), including death resulting therefrom or out of any damage to or loss or destruction of property, real and or personal (including property of COMPANY, CONTRACTOR, and any subcontractor, and including tools and equipment whether owned, rented, or used by CONTRACTOR, any subcontractor, or any workman) in any manner based upon, occasioned by , or attributable orrelated to the performance, whether by the CONTRACTOR or any subcontractor, of the Work or any part thereof, and CONTRACTOR shall at its own expense defend any and all actions based thereon, except where said personal injury or property damage is caused by the negligence of COMPANY or COMPANY'S employees. Any loss, damage, cost expense or attorney's fees incurred by COMPANY in connection with the foregoing may, in addition to other remedies, be deducted from CONTRACTOR'S compensation, then due or thereafter to become due. COMPANY shall effect for the benefit of CONTRACTOR a waiver of subrogation on the existing facilities, including consequential damages such as, but not by way of limitation, loss of profit and loss of product or plant downtime but excluding any deductibles which shall exist as at the date of this CONTRACT; provided, however, that saidwaiver of subrogation shall be expanded to include all said deductible amounts on the acceptance of the Work by COMPANY. "
Comment
: This clause provides the contractor considerable relief. He still has unlimited exposure for injury to all persons and third party property but only to the extent caused by the contractor's negligence. The "sole" negligence issue does not arise. Furthermore, the contractor's liability for damages to the owner's property-a major concern for contractors working in
Example 8-3: An Example Contract Provision with Low Risk Allocation to Contractor
"CONTRACTOR hereby agrees to indemnify and hold COMPANY and/or any parent, subsidiary, or affiliate, or COMPANY and/or officers, agents, or employees of any of them, harmless from and against any loss or liability arising directly or indirectly out of any claim or cause of action for loss or damage to property including, but not limited to, CONTRACTOR'S property and COMPANY'S property and for injuries to or death of persons including but not limited to CONTRACTOR'S employees, caused by or resulting from the performance of the work by CONTRACTOR, its employees, agents, and subcontractors and shall, at the option of COMPANY, defend COMPANY at CONTRACTOR'S sole expense in any litigation involving the same regardless of whether such work is performed by CONTRACTOR, its employees, or by its subcontractors, their employees, or all or either of them. In all instances, CONTRACTOR'Sindemnity to COMPANY shall be limited to the proceeds of CONTRACTOR'S umbrella liability insurance coverage. "
Comment : With respect to indemnifying the owner, the contractor in this provision has minimal out-of-pocket risk. Exposure is limited to whatever can be collected from the contractor's insurance company.
Back to top
All owners want quality construction with reasonable costs, but not all are willing to share risks and/or provide incentives to enhance the quality of construction. In recent
Many public owners have been the victims of their own schemes, not only because of the usual requirement in letting contracts of public works through competitive bidding to avoid favoritism, but at times because of the sheer weight of entrenched bureaucracy. Some contractors steer away from public works altogether; others submit bids at higher prices to compensate for the
Since most claims and disputes arise most frequently from lump sum contracts for both public and private owners, the following factors associated with lump sum contracts are particularly noteworthy:
An unbalanced bid refers to raising the unit prices on items to be completed in the early stage of the project and lowering the unit prices on items to be completed in the later stages. The purpose of this practice on the part of the contractor is to ease its
One of the most contentious issues in contract provisions concerns the payment for change orders. The owner and its engineer should have an
In some projects, the contract provisions may allow the contractor to provide alternative design and/or construction technology. The owner may impose different mechanisms for pricing these changes. For example, a contractor may suggest a design or construction method change that fulfills the performance requirements. Savings due to such changes may accrue to the contractor or the owner, or may be divided in some fashion between the two. The contract provisions must reflect the owners risk-reward objectives in calling for alternate design and/or construction technology. While innovations are often sought to save money and time,
In spite of admonitions and good intentions for better planning before initiating a construction project, most owners want a facility to be in operation as soon as possible once a decision is made to proceed with its construction. Many construction contracts contain provisions of penalties for late completion beyond a specified deadline; however, unless such provisions are accompanied by similar incentives for early completion, they may be
Example 8-4: Arkansas Rice Growers Cooperative Association v. Alchemy Industries
A 1986 court case can illustrate the assumption of risk on the part of contractors and design professionals. [3] The Arkansas Rice Growers Cooperative contracted with Alchemy Industries, Inc. to provide engineering and construction services for a new facility intended to generateBack to topsteam by burning rice hulls. Under the terms of the contract, Alchemy Industries guaranteed that the completed plant would be capable of "reducing a minimum of seven and one-half tons of rice hulls per hour to an ash and producing a minimum of 48 million BTU's perhour of steam at 200pressure." Unfortunately, the finished plant did not meet this performance standard, and the Arkansas Rice Growers Cooperative Association sued Alchemy Industries and its subcontractors for breach of warranty. Damages of almost $1.5 million were awarded to the Association. pounds
While construction contracts serve as a means of pricing construction, they also structure the allocation of risk to the various parties involved. The owner has the sole power to decide what type of contract should be used for a specific facility to be constructed and to set forth the terms in a
In a lump sum contract, the owner has essentially assigned all the risk to the contractor, who in
In a unit price contract, the risk of inaccurate estimation of uncertain quantities for some key tasks has been removed from the contractor. However, some contractors may submit an "unbalanced bid" when it discovers large discrepancies between its estimates and the owner's estimates of these quantities. Depending on the confidence of the contractor on its own estimates and its
For certain types of construction involving new technology or extremely pressing needs, the owner is sometimes forced to assume all risks of cost overruns. The contractor will receive the actual direct job cost plus a fixed percentage, and have little incentive to reduce job cost. Furthermore, if there are pressing needs to complete the project, overtime payments to workers are common and will further increase the job cost. Unless there are compelling reasons, such as the urgency in the construction of military installations, the owner should not use this type of contract.
Under this type of contract, the contractor will receive the actual direct job cost plus a fixed fee, and will have some incentive to complete the job quickly since its fee is fixed regardless of the duration of the project. However, the owner still assumes the risks of direct job cost
For this type of contract, the contractor agrees to a penalty if the actual cost exceeds the estimated job cost, or a reward if the actual cost is below the estimated job cost. In return for taking the risk on its own estimate, the contractor is allowed a variable percentage of the direct job-cost for its fee. Furthermore, the project duration is usually specified and the contractor must abide by the deadline for completion. This type of contract allocates considerable risk for cost overruns to the owner, but also provides incentives to contractors to reduce costs as much as possible.
This is another form of contract which specifies a penalty or reward to a contractor, depending on whether the actual cost is greater than or less than the contractor's estimated direct job cost. Usually, the percentages of savings or overrun to be shared by the owner and the contractor are predetermined and the project duration is specified in the contract. Bonuses or penalties may be stipulated for different project completion dates.
When the project scope is well defined, an owner may choose to ask the contractor to take all the risks, both in terms of actual project cost and project time. Any work change orders from the owner must be extremely minor if at all, since performance specifications are provided to the owner at the outset of construction. The owner and the contractor agree to a project cost guaranteed by the contractor as maximum. There may be or may not be additional provisions to share any savings if any in the contract. This type of contract is particularly suitable for turnkey operation.
Back to top
Regardless of the type of construction contract selected by the owner, the contractor recognizes that the actual construction cost will never be identical to its own estimate because of imperfect information. Furthermore, it is common for the owner to place work change orders to modify the original scope of work for which the contractor will receive additional payments as stipulated in the contract. The contractor will use different
In order to illustrate the relative costs of several types of construction contracts, the pricing mechanisms for such construction contracts are formulated on the same direct job cost plus corresponding markups reflecting the risks. Let us adopt the following notation:
N
1.
At the time of a contract award, the contract price is given by:
| (8.1) |
|
The underestimation of the cost of work in the original contract is defined as:
| (8.2) |
|
Then, at the completion of the project, the contractor's actual cost for the original scope of work is:
| (8.3) |
|
For various types of construction contracts, the contractor's markup and the price for construction agreed to in the contract are shown in Table 8-1. Note that at the time of contract award, it is assumed that A = E, even though the effects of underestimation on the contractor's gross profits are different for various types of construction contracts when the actual cost of the project is assessed upon its completion.
| Type of Contract | Markup | Contract Price |
|
1. Lump sum
2. Unit price 3. Cost plus fixed % 4. Cost plus fixed fee 5. Cost plus variable % 6. Target estimate 7. Guaranteed max cost |
M = (R +R
1
)E
M = (R + R 2 )E M = RA = RE M = RE M = R (2E - A) = RE M = RE + N (E-A) = RE M = (R + R 3 )E |
B = (1 + R + R
1
)E
B = (1 + R + R 2 )E B = (1 + R)E B = (1 + R)E B = (1 + R)E B = (1 + R)E B = (1 + R + R 3 )E |
Payments of change orders are also different in contract provisions for different types of contracts. Suppose that payments for change orders agreed upon for various types of contracts are as shown in column 2 of Table 8-2. The owner's actual payments based on these provisions as well as the incentive provisions for various types of contracts are given in column 3 of Table 8-2. The corresponding contractor's profits under various contractual arrangements are shown in Table 8-3.
| Type of Contract | Change Order Payment | Owner's Payment |
|
1. Lump sum
2. Unit price 3. Cost plus fixed % 4. Cost plus fixed fee 5. Cost plus variable % 6. Target estimate 7. Guaranteed max cost |
C(1 + R + R
1
)
C(1 + R + R 2 ) C(1 + R) C C(1 + R) C |
P = B + C(1 + R + R
1
)
P = (1 + R + R 2 )A + C P = (1 + R)(A + C) P = RE + A + C P = R (2E - A + C) + A + C P = RE + N (E - A) + A + C P = B |
| Type of Contract | Profit from Change Order | Contractor's Gross Profit |
|
1. Lump sum
2. Unit price 3. Cost plus fixed % 4. Cost plus fixed fee 5. Cost plus variable % 6. Target estimate 7. Guaranteed max cost |
C(R + R
1
)
C(R + R 2 CR CR -C |
F = E - A + (R + R
1
)(E + C)
F = (R + R 2 )(A + C) F = R (A + C) F = RE F = R (2E - A + C) F = RE + N (E - A) F = (1 + R + R 3 )E - A - C |
It is important to note that the equations in Tables 8-1 through 8-3 are
Example 8-5: Contractor's Gross Profits under Different Contract Arrangements
Consider a construction project for which the contractor's original estimate is $6,000,000. For various types of contracts, R = 10%, R 1 = 2%, R 2 = 1%, R 3 = 5% and N = 0.5. The contractor is not compensated for change orders under the guaranteed maximum cost contract if the total cost for the change orders is within 6% ($360,000) of the original estimate. Determine the contractor's gross profit for each of the seven types of construction contracts for each of the following conditions.
(a) U = 0, C = 0
(b) U = 0, C = 6% E = $360,000
(c) U = 4% E = $240,000, C = 0
(d) U = 4% E = $240,000 C = 6% E = $360,000
(e) U = -4% E = -$240,000, C = 0
(f) U = -4% E = -$240,000, C = 6% E = $360,000
In this example, the percentage markup for the cost plus fixed percentage contract is 10% which is used as the bench mark for comparison. The percentage markup for the lump sum contract is 12% while that for the unit price contract is 11%, reflecting the degrees of higher risk. The fixed fee for the cost plus fixed fee is based on 10% of the estimated cost, which is comparable to the cost plus fixed percentage contract if there is no overestimate or underestimate in cost. The basic percentage markup is 10% for both the cost plus variable percentage contract and the target
| Type of Contract |
U=0
C=0 |
U=0
C=6%E |
U=4%E
C=0 |
U=4%E
C=6%E |
U=-4%E
C=0 |
U=-4%E
C=6%E |
|
1. lump sum
2. unit price 3. cost + fixed % 4. cost + fixed fee 5. cost + Var % 6. target estimate 7. guar. max. cost |
$720
660 600 600 600 600 900 |
$763
700 636 600 636 600 540 |
$480
686 624 600 576 480 660 |
$523
726 660 600 616 480 300 |
$960
634 576 600 624 720 1,140 |
$1,003
674 612 600 660 720 780 |
Example 8-6: Owner's Payments under Different Contract Arrangements
Using the data in Example 8-5, determine the owner's actual payment for each of the seven types of construction contracts for the same conditions of U and C. The results of computation are shown in Table 8-5.
| Type of Contract |
U=0
C=0 |
U=0
C=6%E |
U=4%E
C=0 |
U=4%E
C=6%E |
U=-4%E
C=0 |
U=-4%E
C=6%E |
|
1. lump sum
2. unit price 3. cost + fixed % 4. cost + fixed fee 5. cost + Var % 6. target estimate 7. guar. max. cost |
$6,720
6,660 6,600 6,600 6,600 6,600 6,900 |
$7,123
7,060 6,996 6,960 6,996 6,960 6,900 |
$6,720
6,926 6,864 6,840 6,816 6,720 6,900 |
$7,123
7,326 7,260 7,200 7,212 7,080 6,900 |
$6,720
6,394 6,336 6,360 6,384 6,480 6,900 |
$7,123
6,794 6,732 6,720 6,780 6,840 6,900 |
Competitive bidding on construction projects involves decision making under uncertainty where one of the greatest sources of the uncertainty for each bidder is due to the unpredictable nature of his
It is useful to think of a bid as being made up of two basic elements: (1) the estimate of direct job cost, which includes direct labor costs, material costs, equipment costs, and direct filed supervision; and (2) the markup or return, which must be sufficient to cover a portion of general overhead costs and allow a fair profit on the investment. A large return can be assured simply by including a sufficiently high markup. However, the higher the markup, the less chance there will be of getting the job. Consequently a contractor who includes a very large markup on every bid could become bankrupt from lack of business. Conversely, the strategy of bidding with very little markup in order to obtain high volume is also likely to lead to bankruptcy. Somewhere in between the two extreme approaches to bidding lies an "optimum markup" which considers both the return and the
From all
One major concern in bidding competitions is the amount of "money left on the table," of the difference between the winning and the next best bid. The winning bidder would like the amount of "money left on the table" to be as small as possible. For example, if a contractor wins with a bid of $200,000, and the
Some of the major factors
Contractors generally tend to specialize in a submarket of construction and concentrate their work in particular geographic locations. The level of demand in a submarket at a particular time can influence the number of bidders and their bid prices. When work is
All other things being equal, the probability of winning a contract diminishes as more bidders participate in the competition. Consequently, a contractor
The bidding strategy of some contractors are influenced by a policy of minimum percentage markup for general overhead and profit. However, the percentage markup may also reflect additional factors stipulated by the owner such as high retention and slow payments for completed work, or perceptions of uncontrollable factors in the economy. The intensity of a contractor's efforts in bidding a specific project is influenced by the contractor's
A final important consideration in forming bid prices on the part of contractors are the possible special advantages enjoyed by a particular firm. As a result of lower costs, a particular contractor may be able to impose a higher profit markup yet still have a lower total bid than competitors. These lower costs may result from
Negotiation is another important mechanism for arranging construction contracts. Project managers often find themselves as
In conducting negotiations between two parties, each side will have a series of objectives and constraints. The overall objective of each party is to obtain the most favorable, acceptable agreement. A two party, one issue negotiation illustrates this fundamental point. Suppose that a developer is willing to pay up to $500,000 for a particular plot of land, whereas the owner would be willing to sell the land for $450,000 or more. These maximum and minimum sales prices represent
constraints
on any eventual agreement. In this example, any purchase price between $450,000 and $500,000 is acceptable to both of the involved parties. This range represents a
With different constraints, it might be impossible to reach an agreement. For example, if the owner was only willing to sell at a price of $550,000 while the developer remains willing to pay only $500,000, then there would be no possibility for an agreement between the two parties. Of course, the two parties typically do not know at the beginning of negotiations if agreements will be possible. But it is quite important for each party to the negotiation to have a sense of their own reservation price , such as the owner's minimum selling price or the buyer's maximum purchase price in the above example. This reservation price is equal to the value of the best alternative to a negotiated agreement.
Poor negotiating strategies adopted by one or the other party may also preclude an agreement even with the existence of a feasible agreement range. For example, one party may be so demanding that the other party simply breaks off negotiations. In effect, negotiations are not a well behaved solution methodology for the resolution of disputes.
The possibility of negotiating failures in the land sale example highlights the importance of negotiating style and strategy with respect to
In light of these tactical problems, it is often beneficial to all parties to adopt objective standards in determining appropriate contract provisions. These standards would prescribe a particular agreement or a method to
With additional issues, negotiations become more complex both in procedure and in result. With respect to procedure, the sequence in which issues are defined or considered can be very important. For example, negotiations may proceed on an issue-by-issue basis, and the outcome may depend upon the exact sequence of issues
The notion of Pareto optimal agreements can be introduced to identify negotiated agreements in which no change in the agreement can
Figure 8-1 Illustration of a Pareto Optimal Agreement Set
The definition of Pareto optimal agreements allows one to assess at least one aspect of negotiated outcomes. If two parties arrive at an inferior agreement (such as point A in Figure 8-1), then the agreement could be improved to the benefit of both parties. In contrast, different Pareto optimal agreements (such as points B and C in Figure 8-1) can represent widely different results to the individual parties but do not have the possibility for joint improvement.
Of course, knowledge of the concept of Pareto optimal agreements does not automatically give any guidance on what might constitute the best agreements. Much of the skill in contract negotiation comes from the ability to invent new options that represent mutual gains. For example, devising contract incentives for speedier completion of projects may result in benefits to both contractors and the owner.
Example 8-7: Effects of different value perceptions.
Suppose that the closing date for sale of the land in the previous case must also be decided in negotiation. The current owner would like to delay the sale for six months, which would represent rental savings of $10,000. However, the developer estimates that the cost of a six month delay would be $20,000. After negotiation, suppose that a purchase price of $475,000 and a six month purchase delay are agreed upon. This agreement is acceptable but not optimal for both parties. In particular, both sides would be better off if the purchase price was increased by $15,000 and immediate closing instituted. The current owner would receive an additional payment of $15,000, incur a cost of $10,000, and have a net gain of $5,000. Similarly, the developer would pay $15,000 more for the land but save $20,000 in delay costs. While this superior result may seem obvious and easily achievable, recognizing such opportunities during a negotiation becomes increasingly difficult as the number and complexity of issues increases.Back to top
This construction negotiation game simulates a contract negotiation between a utility, "CMG Gas" and a design/construct firm, "Pipeline Constructors, Inc." [4] The negotiation involves only two parties but multiple issues. Participants in the game are assigned to represent one party or the other and to negotiate with a designated partner. In a class setting, numerous negotiating
CMG Gas has the opportunity to provide natural gas to an automobile factory under construction. Service will require a new sixteen mile pipeline through farms and light forest. The terrain is hilly with moderate slopes, and equipment access is relatively good. The pipeline is to be buried three feet deep. Construction of the pipeline itself will be contracted to a qualified design/construction firm, while required compression
stations and ancillary work will be done by CMG Gas. As project manager for CMG Gas, you are about to enter negotiations with a local contractor, "Pipeline Constructors, Inc." This firm is the only local contractor qualified to handle such a large project. If a suitable contract agreement cannot be reached, then you will have to break off negotiations soon and turn to another company.
The Pipeline Constructors, Inc. instructions offers a similar overview.
To focus the negotiations, the issues to be decided in the contract are already defined:
A final contract requires an agreement on each of these issues, represented on a form signed by both negotiators.
As a further aid, each participant is provided with additional information and a scoring system to
The two firms have differing perceptions of the desirability of different agreements. In some cases, their views will be directly conflicting. For example, increases in a flat fee imply greater profits for Pipeline Constructors, Inc. and greater costs for CMG Gas. In some cases, one party may feel strongly about a particular issue, whereas the other is not particularly
After examining the project site, your company's estimators are convinced that the project can be completed in thirty-six weeks. In bargaining for the duration, keep two things in mind; the longer past thirty-six weeks the contract duration is, the more money that can be made off the "bonuses for being early" and the
Throughout the project the gas company will want progress reports. These reports take time to compile and therefore the fewer you need to submit, the better. In addition, State law dictates that the Required Standard Report be used unless the contractor and the owner agree otherwise. These standard reports are even more time consuming to produce than more traditional reports.
The State Legislature is considering a law that requires accurate drawings and markers of all pipelines by all utilities. You would prefer not to conform to this uncertain set of requirements, but this is negotiable.
What type of contract and the amount your company will be paid are two of the most important issues in negotiations. In the Flat Fee contract, your company will receive an agreed amount from CMG Gas . Therefore, when there are any delay or cost overruns, it will be the full responsibility of your company. with this type of contract, your company assumes all the risk and will in turn want a higher price. Your estimators believe a cost and contingency amount of 4,500,000 dollars. You would like a higher fee, of course.
With the Cost Plus Contract, the risk is shared by the gas company and your company. With this type of contract, your company will bill
CMG Gas
for all of its costs, plus a specified percentage of those costs. In this case, cost overruns will be paid by the gas company. Not only does the percentage above cost have to be decided upon but also whether or not your company will allow a Field Clerk from the gas company to be at the job site to monitor
Finally, your company is worried whether the gas company will obtain the land rights to lay the pipe. Therefore, you should demand a penalty for the potential delay of the project starting date.
In order to
Throughout the project you will want progress reports. The more often these reports are received, the better to monitor the progress. State law dictates that the Required Standard Report be used unless the contractor and the owner agree otherwise. These reports are very detailed and time consuming to review. You would prefer to use the traditional CMG Gas reports.
The state legislature is considering a law that requires accurate drawings and markers of all pipelines by all utilities. For this project it will cost an additional $250,000 to do this now, or $750,000 to do this when the law is passed.
One of the most important issues is the type of contract, and the amount of be paid. The Flat Fee contract means that CMG Gas will pay the contractor a set amount. Therefore, when there are delays and cost overruns, the contractor assumes full responsibility for the individual costs. However, this evasion of risk has to be paid for and results in a higher price. If Flat Fee is chosen, only the contract price is to be determined. Your company's estimators have determined that the project should cost about $5,000,000.
The Cost Plus Percent contract may be cheaper, but the risk is shared. With this type of contract, the contractor will bill the gas company for all costs, plus a specified percentage of those costs. In this case, cost overruns will be paid by the gas company. If this type of contract is chosen, not only must the profit percentage be chosen, but also whether or not a gas company representative will be allowed on site all of the time acting as a Field Clerk, to ensure that a proper amount of material and labor is billed. The usual percentage agreed upon is about ten percent.
Contractors also have a concern whether or not they will receive a penalty if the gas right-of-way is not obtained in time to start the project. In this case, CMG Gas has already secured the right-of-ways. But, if the penalty is too high, this is a dangerous precedent for future negotiations. However, you might try to use this as a bargaining tool.
Example 8-8: An example of a negotiated contract
A typical contract resulting from a simulation of the negotiation between CMG Gas and Pipeline Constructors, Inc. appears in Table 8-6. An agreement with respect to each pre-defined issue is included, and the resulting contract signed by both negotiators.
| Duration | 38 weeks |
| Penalty for Late Completion | $6,800 per day |
| Bonus for Early Completion | $0 per day |
| Report Format | traditional CMG form |
| Frequency of Progress Reports | weekly |
| Conform to Pending Pipeline Marking Legislation | yes |
| Contract Type | flat fee |
| Amount of Flat Fee | $5,050,000 |
| Percentage of Profit |
Not
|
| CMG Gas Clerk on Site | yes |
| Penalty for Late Starting Date | $3,000 per day |
Signed:
CMG Gas Representative |
|
Example 8-9: Scoring systems for the negotiated contract
To measure the performance of the negotiators in the previous example, a scoring system is needed for the representative of Pipeline Constructors, Inc. and another scoring system for the representative of CMG Gas. These scoring systems for the companies associated with the issues described in Example 8-7 are designated as system A.In order to make the negotiating game
viable for classroom use, another set of instructions for each company is described in this example, and the associated scoring systems for the two companies are designated as System B. In each game play, the instructor may choose a different combination of instructions and negotiatingteams , leading to four possible combinations of scoring systems for Pipeline Constructors, Inc. and CMG Gas. [5]
In order to help you, your boss has left you with a scoring table for all the issues and alternatives. Two different scoring systems are listed here; you will be assigned to use one or the other. Instructions for scoring system A are included in Section 8.9. The instructions for scoring system B are as
After examining the site, your estimator believes that the project will require 38 weeks. You are happy to conform with any reporting or pipeline marking system, since your computer based project control and design systems can easily produce these submissions. You would prefer to delay the start of the contract as long as possible, since your forces are busy on another job; hence, you do not want to impose a penalty for late start. Try to maximize the amount of points, as they reflect profit brought into your company, or a cost savings. In
SCORING FOR PIPELINE CONSTRUCTORS, INC.
NOTE: NA means not acceptable and the deal will not be approved by your boss with any of these provisions. also, the alternatives listed are the only ones in the context of this problem; no other alternatives are acceptable.
| 1. COMPLETION DATE | ||||||
| System A | System B | |||||
|
Under 36 Weeks
36 weeks 37 weeks 38 weeks 39 weeks 40 weeks |
NA
+5 +10 +20 +40 |
NA
NA -10 +10 +20 |
||||
| 2. REPORTS | ||||||
|
State Standard Report
CMG Reports |
-20
-5 |
|
||||
| 3. PENALTY FOR LATENESS ($ PER DAY) | ||||||
| DURATION | (WEEKS) | |||||
|
Scoring System A
Scoring System B |
36
37 |
37
38 |
38
39 |
39
40 |
40
41 |
|
|
0 - 999
1,000 - 1,999 2,000 - 2,999 3,000 - 3,999 4,000 - 4,999 5,000 - 5,999 6,000 - 6,999 7,000 - 7,999 Over 8,000 |
-1
-2 -4 -6 -8 -11 -14 -18 NA |
-1
-2 -3 -5 -7 -9 -12 -14 NA |
-1
-2 -3 -4 -5 -7 -9 -11 NA |
-1 -2 -3 -4 -5 -6 -7 NA |
-1 -1 -2 -2 -3 -3 NA |
|
| 4. BONUS FOR BEING EARLY ($ PER DAY) | ||||||
|
Scoring System A
Scoring System B |
36
37 |
37
38 |
38
39 |
39
40 |
40
41 |
|
|
0 - 999
1,000 - 1,999 2,000 - 2,999 3,000 - 3,999 4,000 - 4,999 5,000 - 5,999 6,000 - 6,999 7,000 - 7,999 8,000 - 8,999 9,000 - 9,999 Over 10,000 |
1 2 3 4 5 6 7 8 |
2 4 6 8 10 12 14 16 18 |
2 4 6 8 10 14 18 22 26 30 |
2 4 6 10 14 18 24 28 32 36 |
2
2 4 8 12 16 22 28 36 40 45 |
|
| 5. CONFORM TO PENDING LEGISLATION (MARKING PIPELINES) | ||||||
| A | B | |||||
|
Yes
No |
+5
+15 |
+10
+10 |
||||
| 6. HOW OFTEN FOR THE PROGRESS REPORTS | ||||||
| A | B | |||||
|
Daily
Weekly Bi-weekly Monthly |
NA
-20 -10 -6 |
|
||||
| 7. CONTRACT TYPE | ||||||
| A | B | |||||
|
Flat Fee
Cost + X% |
5
+25 |
5
+25 |
||||
|
If Cost + X% do parts 9 and 10 and skip part 8. |
||||||
| 8. FLAT FEE ($) | ||||||
| A | B | |||||
|
Below 4,500,000
Over 4,500,000 |
NA
+1 for each 10,000 |
-15 for each 10,000
+2 for each 10,000 |
||||
| 9. IF COST PLUS X% | ||||||
| A | B | |||||
|
Below 6%
6% 7% 8% 9% 10% 11% 12% 13% 14% Over 14% |
NA
+250 +375 +450 +475 +500 +525 +550 +600 +725 +900 |
NA
NA +300 +330 +360 +400 +440 +480 +540 +600 +800 |
||||
| 10. GAS CO. FIELD CLERK ON SITE | ||||||
| A | B | |||||
|
Yes
No |
|
+10 |
||||
| 11. PENALTY FOR DELAYED STARTING DATE DUE TO GAS COMPANY ERROR ($ PER DAY) | ||||||
| A | B | |||||
|
0 - 499
500 - 1499 1500 - 2499 1500 - 3499 3500 - 4499 4500 - 5499 5500 - 6499 6500 - 7499 7500 or more |
NA
-6 -4 -2 -1 +1 +2 +4 |
NA
-10 -7 -5 -3 -1 +3 +6 |
||||
In order to help you, your boss has left you with a scoring table for all the issues and alternatives. Two different scoring systems are listed here; you will be assigned to use one or the other. Instructions for scoring system A are included in Section 8.9. The instructions for scoring system B are described as follows:
Your contract with the automobile company provides an incentive for completion of the pipeline earlier than 38 weeks and a penalty for completion after 38 weeks. To insure
Try to maximize the number of points from the final contract provisions; this corresponds to minimizing costs. Do not discuss your scoring systems with Pipeline Constructors, Inc.
SCORING SYSTEM FOR CMG GAS
NOTE: NA means not acceptable and the deal will not be approved by your boss with any of these provisions. If you can't negotiate a contract, your score will be +450. Also, the alternatives listed are the only ones in the context of this problem no other alternatives are acceptable.
| 1. DURATION | POINTS | |||||
| System A | System B | |||||
|
Over 40 weeks
40 weeks 39 weeks 38 weeks 37 weeks 0-36 weeks |
NA
+2 +4 +5 +6 |
-40
-10 +2 +8 +14 +14 |
||||
| 2. REPORTS | A | B | ||||
|
Required Standard Report
"Traditional" CMG Gas Reports |
+2
+10 |
|
||||
| 3. PENALTY FOR LATENESS ($ PER DAY) | ||||||
| DURATION | (WEEKS) | |||||
|
Scoring System A
Scoring System B |
36
38 |
37
39 |
38
40 |
39
41 |
40
42 |
|
|
0 - 999
1,000 - 1,999 2,000 - 2,999 3,000 - 3,999 4,000 - 4,999 5,000 - 5,999 6,000 - 6,999 7,000 - 7,999 8,000 - 8,999 9,000 - 9,999 10,000 or more |
NA
9 10 11 12 13 14 15 16 17 18 |
NA
7 9 10 11 12 13 15 15 16 16 |
NA
6 8 9 10 11 12 13 14 15 15 |
NA
3 5 6 7 8 9 11 12 13 13 |
NA
2 4 5 6 7 8 9 10 11 |
|
| 4. BONUS FOR BEING EARLY ($ PER DAY) | ||||||
| A | B | |||||
|
8000 or more
7000 - 7999 6000 - 6999 5000 - 5999 4000 - 4999 3000 - 3999 2000 - 2999 1000 - 1999 0 - 999 |
NA
+3 +6 +8 +10 +12 +13 +14 +15 |
-5
-2 -1 +5 +7 +9 +13 +17 |
||||
| 5. CONFORM TO PENDING LEGISLATION (MARKING PIPELINES) | ||||||
| A | B | |||||
|
Yes
No |
+25
-25 |
NA |
||||
| 6. HOW OFTEN FOR THE PROGRESS REPORTS | ||||||
| A | B | |||||
|
Daily
Weekly Bi-weekly Monthly |
+45
+50 +30 NA |
+50
+30 +10 +5 |
||||
| 7. CONTRACT TYPE | ||||||
| A | B | |||||
|
Flat Fee
Cost + X% |
25
|
25
|
||||
|
If Cost + X% do parts 9 and 10 and skip part 8. |
||||||
| 8. FLAT FEE ($) | ||||||
| A | B | |||||
|
Over 5,000,000
0 - 5,000,000 |
NA
+1 for each 10,000 below 5,000,000 |
NA
+1 for each 10,000 below 5,000,000 |
||||
| 9. IF COST PLUS X% | ||||||
| A | B | |||||
|
Below 5%
5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% Over 14% |
+950
+800 +700 +600 +550 +525 +500 +475 +450 +400 +300 +200 NA |
+700
+660 +620 +590 +570 +550 +535 +500 +440 +380 +300 +100 +10 |
||||
| 10. GAS CO. FIELD CLERK ON SITE | ||||||
| A | B | |||||
|
Yes
No |
+20
+5 |
+10
|
||||
| 11. PENALTY FOR DELAYED STARTING DATE DUE TO UNAVAILABLE RIGHT-OF-WAYS ($ PER DAY) | ||||||
| A | B | |||||
|
0 - 1,999
2,000 - 3,999 4,000 - 5,999 6,000 - 7,999 8,000 - 9,999 10,000 or more |
+10
+8 +6 +4 +2 NA |
+3
+2 +1 -10 -20 |
||||
Once a contract is reached, a variety of problems may emerge during the course of work. Disputes may arise over quality of work, over responsibility for delays, over appropriate payments due to changed conditions, or a
The most prominent mechanism for dispute resolution is adjudication in a court of law. This process tends to be expensive and time consuming since it involves legal representation and waiting in queues of cases for available court times. Any party to a contract can bring a suit. In adjudication, the dispute is decided by a neutral, third party with no necessary specialized expertise in the disputed subject. After all, it is not a prerequisite for judges to be familiar with construction procedures! Legal procedures are highly structured with rigid, formal rules for presentations and fact finding. On the positive side, legal adjudication strives for consistency and predictability of results. The results of previous cases are published and can be used as
Negotiation among the contract parties is a second important dispute resolution mechanism. These negotiations can involve the same sorts of concerns and issues as with the original contracts. Negotiation typically does not involve third parties such as judges. The negotiation process is usually informal, unstructured and relatively inexpensive. If an agreement is not reached between the parties, then adjudication is a possible remedy.
A third dispute resolution mechanism is the resort to arbitration or mediation and conciliation. In these procedures, a third party serves a central role in the resolution. These outside parties are usually chosen by mutually agreement of the parties involved and will have specialized knowledge of the dispute subject. In arbitration, the third party may make a decision which is binding on the participants. In mediation and conciliation, the third party serves only as a facilitator to help the participants reach a mutually acceptable resolution. Like negotiation, these procedures can be informal and unstructured.
Finally, the high cost of adjudication has inspired a series of non-traditional dispute resolution mechanisms that have some of the characteristics of judicial proceedings. These mechanisms include:
Some of these procedures may be court sponsored or required for particular types of disputes.
While these various disputes resolution mechanisms involve varying costs, it is important to note that the most important mechanism for reducing costs and problems in dispute resolution is the reasonableness of the initial contract among the parties as well as the competence of the project manager.
Back to top
|
C = 6%E
C = 6%E C = 6%E |
P = R(2E - A + C) + A + C + DT(1 + 0.4C/E)
The value of T is set at $5,000 per day, and the project is completed 30 days behind schedule. If all other conditions remain unchanged, find the contractor's profit and the owner's actual payment under this contract for the given conditions of U and C.
|
C = 0
C = 4% E = $120,000 C = 0 C = 4% E = 120,000 C = 0 C = 4% E = 120,000 |
|
C = 5%E
C = 5%E C = 5%E |
P = R(2E - A + C) + A + C + DT(1 + 0.2C/E)
The value of T is set at $ 10,000 per day, and the project is completed 20 days ahead schedule. If all other conditions remain unchanged, find the contractor's profit and the owner's actual payment under this contract for the given conditions of U and C.
Pipeline Constructors Inc.CMG Gas a.
b.
c.
d. System A
System A
System B
System BSystem A
System B
System A
System BSince the scoring systems are confidential information, your instructor will not disclose the combination used for the assignment. Your instructor may divide the class into groups of two students, each group acting as negotiators representing the two companies in the game. To keep the game interesting and fair, do not try to find out the scoring system of your negotiating counterpart . To seek insider information is unethical and illegal!
1. These examples are taken directly from A Construction Industry Cost Effectiveness Project Report, "Contractual Arrangements," The Business Roundtable, New York, Appendix D, 1982. Permission to quote this material from the Business Roundtable is gratefully
2. See C.D. Sutliff and J.G. Zack, Jr. "Contract Provisions that Ensure Complete Cost Disclosures", Cost Engineering , Vol. 29, No. 10, October 1987, pp. 10-14. Back
3. Arkansas Rice Growers v. Alchemy Industries, Inc., United States Court of Appeals, Eighth Circuit, 1986. The court decision appears in 797 Federal Reporter, 2d Series, pp. 565-574. Back
4. This game is further described in W. Dudziak and C. Hendrickson, "A Negotiation Simulation Game," ASCE Journal of Management in Engineering , Vol. 4, No. 2, 1988. Back
5. To undertake this exercise, the instructor needs to divide students into negotiating teams, with each individual assigned scoring system A or B. Negotiators will represent Pipeline Constructors, Inc. or CMG Gas. Negotiating pairs should not be told which scoring system their counterpart is assigned. Back
| Previous Chapter | Table of Contents | Next Chapter |